In order to meet the rapidly growing power demand and to enhance the reliability and security of power supply in North-East of Riyadh city, will be constructed the new 380/132/13.8kV Substation of Ashbailyah. This one will be connected to the existing 380kV Substation through underground cables.
This reinforcement will require the expansion of the existing 380kV GIS Nasim Substation by installing two new bays
The contract was signed last August 19th, 2013. The duration of the project is 27 months. |